Dewatering Chute Success

21-08-2019

Drift Belt De-Watering Chute - Tier 1 Underground Coal Mine In QLD

Below we have a collection of videos from the commissioning/start-up of a recently installed Cove Engineering de-watering chute.

This Cove inline de-watering chute design is the standard approach for other tier 1 miners in the region.

Cove designed the de-watering chute complete with tripper, load station and associated belt regrading structure, implemented in an existing drift belt without the need for additional drive power.

This de-watering chute features a new development that includes capturing both primary and secondary streams to maximise the water removal from the belt.

The de-watering chute and structure was installed successfully in a 3-day outage.

Initial Commissioning - Running Empty and Clean Video Link

Morning after the night before - Running Empty Video Link

Running Dry Coal Video Link

Running Sloppy Coal Video Link

Running Higher Tonnage Dry Coal Video Link